Contract Escalation Clauses

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

In an effort to share the risk of fluctuating materials prices with the contractor, the Department uses several escalation clauses. The Fuel Escalation Clause can be used for any contract greater than $250,000. The Fuel Factor Percentage for a contract is calculated based on the value of selected items in the Engineers Estimate to provide an average fuel usage for the contract items. The Asphalt Escalation Clause is used for any contract with more than 4,000 tons of plantmix. Currently the clause only applies to paving grade asphalts. The Emulsified Asphalt Escalation Clause is intended to minimize the cost effects of price uncertainty to the Contractor and the Department. Prices are the same as AWP Asphalt Prices.

Select a link below to see currently posted escalation prices.

 AWP Asphalt Escalation Prices          

First Workday for Week of: 

 Weekly Average Price Bp & Cp:

8/10/2026   622.22  
8/3/2026   622.22  
 7/27/2026    622.22  
7/20/2026   622.22  
7/13/2026  622.22 
7/6/2026  622.22 
 6/29/2026 640.83 
 6/22/2026 640.83 
 6/15/2026 640.83 
 6/8/2026 640.83 
 6/1/2026 627.78 
5/25/2026  622.22 
 5/18/2026 622.22 
 5/11/2026 619.72 
 5/4/2026 616.94 
 4/27/2026 605.83 
4/20/2026  605.83 
 4/13/2026 601.67 
 4/6/2026 589.44 
 3/30/2026 555.00 
 3/23/2026 555.00 
 3/16/2026 535.83
 3/9/2026 513.06
 3/2/2026 513.06
 2/23/2026 511.39
 2/16/2026 511.39
 2/9/2026 511.39
 2/2/2026 506.67
 1/26/2026 506.67
 1/19/2026 506.67
 1/12/2026 509.44
 1/5/2026 509.44

 

 

Questions on the escalation clauses can be directed to the Construction Division at 775-888-7460.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Download Acrobat Reader Download Windows Media Player Download Word Viewer Download Excel Viewer Download PowerPoint Viewer