Nevada Department of Transportation
Home MenuDocuments
74271 Henderson Interchange CRA
Henderson Interchange - Traffic Safety Analysis Report Final
Henderson Handout
Henderson Interchange PPT Jul 22 2021 (1)
06.14.21.HD Interchange Project Sheet
74271_Henderson Interchange Alternatives Analysis Report_May 2021 (2)
74271_Henderson Interchange Alternatives Analysis Report_May 2021 (2)
COH_Henderson Feasibility Study_FINAL_021920 (1)
COH_Henderson Feasibility Study_FINAL_021920 (1)
COH_Henderson Feasibility Study_FINAL_021920 (1)
COH_Henderson Feasibility Study_FINAL_021920 (1)
74271_Henderson Interchange Alternatives Analysis Report_May 2021 (2)
Attachment 2 74271 Option 2A NEPA E-W Guide Concept Plan 05-04-21
Attachment 2 74271 Option 2A_NEPA_E-W_Guide_Sign_Concept_Plan_05-04-21
Attachment 2 74271 Option 2A_NEPA_E-W_Guide_Sign_Concept_Plan_05-04-21
Attachment 1 74271 Option 3_NEPA_N-S Exhibit 02-04-21
Attachment 1 74271 Option 3_NEPA_E-W Exhibit 02-04-21
Attachment 1 74271 Option 2A_NEPA_N-S Exhibit 04-28-21
Attachment 1 74271 Option 2A_NEPA_E-W Exhibit 04-28-21
Attachment 3 74271 Option 2A_Conceptual MOT Phasing_reduced
Appendix 03 Alternatives Screening Report_reduced
Attachment 2 74271 Option 3_NEPA_N-S_Guide_Sign_Concept_Plan_02-04-21
Attachment 2 74271 Option 3_NEPA_E-W_Guide_Sign_Concept_Plan_02-04-21
Attachment 2 74271 Option 2A_NEPA_N-S_Guide_Sign_Concept_Plan_05-04-21
Attachment 2 74271 Option 2A_NEPA_E-W_Guide_Sign_Concept_Plan_05-04-21
Attachment 1 74271 Option 3_NEPA_N-S Exhibit 02-04-21
Attachment 1 74271 Option 3_NEPA_E-W Exhibit 02-04-21
74271_Henderson Interchange Alternatives Analysis Report_May 2021 (1)
Appendix 17 Limited Geotechnical Assessment (1)
Appendix 16 Drainage Facilities
Appendix 15 FEMA Floodplain Documentation
Appendix 14 TAC Meeting Minutes
Appendix 13 UPRR Coordination
Appendix 12 Summary of COH Hazmat Reports
Appendix 11 Planning and Environmental Linkages
Appendix 10 Public Involvement Activities
Appendix 09 Cost Risk Assessment
Appendix 08 BCA Report
Appendix 07 Cost Estimate Worksheets
Appendix 06 Conceptual Plans
Appendix 05 Bridge Type Selection Study
Appendix 04 Utilities
Appendix 02 Synchro Output
Appendix 01 Traffic Forecasting Memo
HD Interchange Project Sheet
I-15 South Project: Sloan Road to North of Warm Springs Road
Construction underway through December 2025
Project Overview
The Nevada Department of Transportation (NDOT) began improvements along nearly nine miles of Interstate 15 (I-15) South from Sloan Road to north of Warm Springs Road in January 2024. This Project will aid in improving travel-time reliability, serve proposed growth in the area by increasing local mobility and access, and enhance I-15’s operational efficiency. Construction is anticipated to be completed within a 24-month period.
Project features include:
- Widening I-15 from six to eight general-purpose lanes between Sloan Road and St. Rose Parkway
- Widening and restriping I-15 from six to 11 general-purpose lanes between St. Rose Parkway and Blue Diamond Road
- Resurfacing bridges and pavement preservation at the Blue Diamond Interchange
- Construction of 6 new sound walls near qualifying residential areas throughout the corridor
Current and Upcoming Restrictions
8:00 p.m. Sunday, Dec. 7 to 5:00 a.m. Monday, Dec. 8
- Blue Diamond Rd on-ramp to northbound I-15 closed
- Eastbound Blue Diamond Rd to northbound I-15 flyover will remain open
Nightly (8:00 p.m. to 5:00 a.m.) Monday, Dec. 8 and Tuesday, Dec. 9 (2 nights):
- Blue Diamond Rd on-ramp to southbound I-15 closed
8:00 p.m. Tuesday, Dec. 9 to 5:00 a.m. Wednesday, Dec. 10
- St. Rose Pkwy on-ramp to northbound I-15 closed
8:00 p.m. Thursday, Dec. 11 to 5:00 a.m. Friday, Dec. 12
- North and southbound I-15 reduced to one lane between Starr Ave and Sloan Rd
Funding
The total cost for construction is $81 M. The project is paid for with 95% federal and 5% state funds. Funding sources include National Highway Performance Program (NHPP), Surface Transportation Block (STBG) and PROTECT Program grants, and state gas tax.
Contractor
Fisher Industries
Schedule
Below is a general overview of the construction schedule. The schedule is subject to change.
January-June 2024 (Complete):
- Earthwork and widening SB I-15 from St. Rose Pkwy. to Sloan Rd.
- Earthwork and widening SB I-15 from St. Rose
- Concrete grinding at the Sloan Rd. interchange
- Drainage and electrical improvements
- Bridge resurfacing at Blue Diamond Rd.
- Begin forming sound walls
July-December 2024 (Complete):
- Drainage and electrical improvements
- Forming sound walls
- Installing overhead signs
- Rock landscaping
- Fence and guard rail installation
January-June 2025 (Complete):
- Earthwork and widening NB I-15 from Cactus Ave. to Silverado Ranch Blvd.
- Earthwork and widening SB Blue Diamond Rd to Silverado Ranch Blvd.
- Earthwork and widening both SB and NB I-15 from St. Rose Pkwy. to Silverado Ranch Blvd.
- Earthwork and widening NB I-15 from Sloan Rd. to St. Rose Pkwy.
- Drainage and electrical improvements
- Forming sound walls
- Rock landscaping
- Fence and guard rail installation
- Installing overhead signs
July-December 2025:
- Mill and fill existing asphalt NB and SB from Warm Springs Rd. to Sloan Rd.
- Electrical improvements
- Rock landscaping
- Fence and guard rail installation
Traffic Control
Project working hours are nightly, Sunday nights starting at 8 p.m. through Friday evenings at 5 p.m.
- Drivers can expect lane shifts and lane reductions to occur with a reduced speed of 55 MPH.
- During daytime hours, Monday-Friday from 5 a.m. to 8 p.m., three lanes of traffic will be maintained in each direction.
- Traffic will be reduced to one lane of traffic in each direction nightly, Sunday-Friday 8 p.m. to 5 a.m.
Project Background
In 2008, an Environmental Assessment (EA) was prepared for the I-15 South Corridor Improvement Project, addressing the environmental effects of improvements along the I-15 corridor, including a portion of Las Vegas Boulevard South, between Sloan Road and Tropicana Avenue. A Finding of No Significant Impact (FONSI) for the overall project was approved by the Federal Highway Administration on April 20, 2009.
In 2022, a reevaluation of the I-15 South EA and FONSI was done to consider changing conditions and new issues that have transpired over the last several years within the I-15 South project area. The reevaluation of effects of the Phase 2 improvements was approved by FHWA and the project immediately moved forward into design. Design plans were finalized in the summer of 2023.
I-15 South Corridor Improvement Project EA_2008
Public Meeting Presentation_November 2022
Contact
NDOT Project Manager: Mauricio Cardenas, P.E.
mcardenas@dot.nv.gov
(702) 671-8876
NDOT Acting Resident Engineer: Shawn Meagher
shawn.meagher@constructnv.com
(702) 481-2362
For noise complaints, please contact Kevin Van Riel with Fisher Industries at (702) 219-3375 or kvanriel@fisherind.com.