Nevada Department of Transportation
Home MenuDocuments
- Design
- Environmental Services
- Location Services
- Project Management
- Right-of-Way
- Structures Manual
2018 MS4 Permit SWMP Plan_Revised_June of 2024_All_R
SWMP Plan_Revised_November of 2022_All_R
MILEPOST_MARKERS_Shapefile
NV_ROADS_Shapefile
english_2010sm
english_2007sm
NV_Roads_Metadata
NV_MileMarkers_Metadata
NV_MileMarkers_and_Roads.gdb
nv.fhwa.federal aid highway program in nevada.pa.24oct14 ocr
STP 1 DRAFT 5-14-2015 Clean Copy
NDOTCR Handbook Final 4_10_13 version dated 8_5_14 CLEAN version reduced
3-D scanning paleograsshopper poster
2015 NDOT PA Annual Report
Terms Condition 021214
NRS_408
Item 9
Item 8
Item 7
Item 6
Item 5
Item 4
Item 3
Item 2
Item 11
Item 10
Item 1
State Owned Leased Property
Property Inventory
Leases for State Use
AB404[1]
ROW Buy America Policy 8-31-16
Relocation Assistance In Nevada 2012
Nevada Highways and Your Property(1)
NDOT_Right-of-Way_Manual_2011(1)
Upcoming_Construction_Projects
I-15 South Corridor: Via Nobila Interchange
Project Background
In 2008, an Environmental Assessment (EA) was prepared for the I-15 South Corridor Improvement Project,
addressing the environmental effects of improvements along the I-15 corridor, including a portion of Las Vegas
Boulevard South, between Sloan Road and Tropicana Avenue. A Finding of No Significant Impact (FONS!) for the
overall project was approved by the Federal Highway Administration on April 20, 2009. In 2022, a reevaluation of
the I-15 South EA and FONSI was done to consider changing conditions and new issues that have transpired over
the last several years within the I-15 South project area.
I-15 South Corridor Improvement Project EA 2008
Project Overview
The Project is located on Interstate 15 (I-15) in Clark County, Nevada, and will consist of providing access to
the Inspirada Master Planned Community located in West Henderson, Nevada, east of the I-15. The Project
will include construction of a new interchange and extension of Via Nobila, west of Las Vegas Boulevard.
The DEPARTMENT intends to utilize a Design-Bid-Build (DBB) method for delivery of this Project. This
Project is a phase of the I-15 South Corridor and a National Environmental Policy Act (NEPA) Re-Evaluation
for this phase will be completed by the DEPARTMENT’s Environmental Division.
Project Purpose and Need
The project is to provide a grade separated interchange along I-15 at Via Nobila that currently terminates at
Las Vegas Boulevard. The secondary purpose of the project is to widen I-15 to alleviate traffic congestion
along I-15 and accommodate the proposed High-Speed Rail along the median. There were three interchange
alternatives studied to determine the most efficient system. Those included a tight diamond interchange,
single point urban interchange and a diverging diamond interchange.
The diverging diamond interchange was selected because of cost and traffic flow efficiency as depicted in
the following figure:
Funding
The total projected cost for construction is $100M. The project is paid for with 95% federal and 5% state funds. Funding sources include National Highway Performance Program (NHPP), Bridge Formula Program (BFP), and State match funding.
Schedule
The project is currently progressing towards final design completion. Below is a general overview of the
design and construction schedule. The schedule is subject to change.
Final Design Completion: November 2028
Start Construction Phase: Q1 2029
Construction Phase Completion: Q1 2031
Contact
NDOT Project Manager: Mauricio Cardenas, P.E.
mcardenas@dot.nv.gov
(702) 671-8876