Nevada Department of Transportation
Home MenuDocuments
library_periodicals_131014
NDOT_Library_ Account
New_Books_Fall_2014
Research Manual
Winter 2011
Winter 2010
Winter 2009
Winter 2008
Winter 2007
Winter 2006
Winter 2005
Winter 2004
Winter 2003
Winter 2001
Winter 2000
Winter 1999
Winter 1998
Winter 1997
WinterNewsletter 2017
Winter 2013
Fall2011
Fall_2013_Newsletter
Fall 2010
Fall 2009
Fall 2008
Fall 2007
Fall 2006
Fall% 2005
Fall 2004
Fall 2003
Fall% 2002
Fall 2001
Fall 2000
Fall 1999
Fall 1998
Fall% 1997
summer 2011
Summer 2010
Summer 2009
Summer 2008
Summer 2007(1)
Summer 2006
Summer 2004
Summer 2003
Summer 2002
Summer 2001
Summer 2000
Summer 1999
Summer 1998
Summer 1997
Spring_Summer 2013 Newsletter
Spring_Summer 2012
Spring1997
Spring1999
Spring1998
Spring2000
Spring2010
Spring2009
Spring2008
Spring2007
Spring2006
Spring2005
Spring2004
Spring2003
Spring2002
Spring2001
NewsletterSpring2011
I-15 South Corridor: Via Nobila Interchange
Project Background
In 2008, an Environmental Assessment (EA) was prepared for the I-15 South Corridor Improvement Project,
addressing the environmental effects of improvements along the I-15 corridor, including a portion of Las Vegas
Boulevard South, between Sloan Road and Tropicana Avenue. A Finding of No Significant Impact (FONS!) for the
overall project was approved by the Federal Highway Administration on April 20, 2009. In 2022, a reevaluation of
the I-15 South EA and FONSI was done to consider changing conditions and new issues that have transpired over
the last several years within the I-15 South project area.
I-15 South Corridor Improvement Project EA 2008
Project Overview
The Project is located on Interstate 15 (I-15) in Clark County, Nevada, and will consist of providing access to
the Inspirada Master Planned Community located in West Henderson, Nevada, east of the I-15. The Project
will include construction of a new interchange and extension of Via Nobila, west of Las Vegas Boulevard.
The DEPARTMENT intends to utilize a Design-Bid-Build (DBB) method for delivery of this Project. This
Project is a phase of the I-15 South Corridor and a National Environmental Policy Act (NEPA) Re-Evaluation
for this phase will be completed by the DEPARTMENT’s Environmental Division.
Project Purpose and Need
The project is to provide a grade separated interchange along I-15 at Via Nobila that currently terminates at
Las Vegas Boulevard. The secondary purpose of the project is to widen I-15 to alleviate traffic congestion
along I-15 and accommodate the proposed High-Speed Rail along the median. There were three interchange
alternatives studied to determine the most efficient system. Those included a tight diamond interchange,
single point urban interchange and a diverging diamond interchange.
The diverging diamond interchange was selected because of cost and traffic flow efficiency as depicted in
the following figure:
Funding
The total projected cost for construction is $100M. The project is paid for with 95% federal and 5% state funds. Funding sources include National Highway Performance Program (NHPP), Bridge Formula Program (BFP), and State match funding.
Schedule
The project is currently progressing towards final design completion. Below is a general overview of the
design and construction schedule. The schedule is subject to change.
Final Design Completion: November 2028
Start Construction Phase: Q1 2029
Construction Phase Completion: Q1 2031
Contact
NDOT Project Manager: Mauricio Cardenas, P.E.
mcardenas@dot.nv.gov
(702) 671-8876