SR 169 Shoulder Widening and Truck Climbing Lane

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Public Meeting

A public meeting for this project was held on November 15, 2022 at the Moapa Valley Community Center from 4-7 p.m. 

For questions regarding the project or meeting, contact the NDOT project manager Nanette Maxwell: (775) 888-7742, nmaxwell@dot.nv.gov

About the Project

State Route 169 is a two-lane rural major collector, also known as Moapa Valley Boulevard, that begins near the Lake Mead National Recreation Area boundary south of Overton and continues to the Interstate 15 (I-15) Logandale Interchange. NDOT will flatten roadway slopes, provide wider shoulders, a buffered bike lane, and a northbound truck climbing lane. The proposed project will also include additional lanes for turning vehicles at the Waterline Road intersection. The public meeting serves as an opportunity for residents to meet the NDOT project team, view construction information, and ask questions. Construction is anticipated to start in March 2023 and end January 2024.

Project Purpose

This project will enhance safety, drainage, and roadway operations along SR 169 from Canal Avenue to I-15. It will improve pavement condition within the corridor and construct flatter slopes along the edge of the roadway to create a clear zone. Additional pavement will be constructed outside the standard travel lane to serve as a wider shoulder area. Five-foot buffered bike lanes will be added in both directions as well as a four-foot striped median with rumble strips to reduce potential head-on crashes. Additionally, a truck climbing lane will be constructed in the northbound direction, starting at Waterline Road and end approximately one mile north of Waterline Road.

Project Area

SR 169, also known as Moapa Valley Boulevard, begins near the 

Lake Mead National Recreation Area boundary south of Overton and continues to the I-15 Logandale Interchange.

SR 169 Project Limits

• SR 169 from Canal Avenue to the I-15
• Additional Improvements at Waterline Road

 

 

 

 

 

 

 

Project Details

Existing Conditions 

One lane in each direction through entire project. Minimal shoulders and no bike lane.

Existing Conditions

Roadway Section

The new general roadway section will include widened shoulders, a new bike lane, and a buffer between bikes and traffic. A striped median will provide a buffer between opposing traffic along the center of the roadway.

Proposed Standard Roadway Section

Truck Climbing Lane Roadway Section

A new truck climbing lane will be added for northbound traffic just north of Logandale. This section will have a widened shoulder and a buffered bike lane.

Proposed Truck Climbing Lane Roadway Section

Slope Flattening

In addition to widened shoulders, most of the project will include a flattened area extending 17’ from the
new edge of the pavement. This will provide additional space for drivers to pull off the road or regain control.

Slope flattening graphic

Waterline Road

Intersection improvements at Waterline road:

• New SR 169 SB right turn lane with deceleration lane
• New SR 169 NB left turn lane with deceleration lane
• New SR 169 NB acceleration lane

Waterline Road (Labeled)_v2

Schedule and Impacts

Las Vegas Paving Corp. is the contractor for this project. Construction is expected to begin in March 2023 and reach substantial completion by January 2024. 

During Construction, crews will install tortoise fencing, do earthwork and drainage improvements, widen the shoulder and preserve pavement. 

One-Way Pilot Car Operation 

Construction will  include a one-way pilot car operation during working hours (6 a.m. to 4 p.m. Monday through Thursday), March 2023 through October 2023. A 20-minute maximum stop and 30-minute maximum delay is expected during those times.

Public Meeting Materials

Meeting Presentation

Project Area

Project Details

Schedule Impacts

Waterline Road Improvements

Project Fact Sheet